Trial Report No. 93-T87 Contract (access required)

Failure to Identify Wetlands - Construction Delay Type of Action Breach of contract; professional liability claim against engineer Type of Injuries Costs incurred by developer due to one-year delay as a result of failure of engineer to identify wetlands problem Name of Case P&T Associates v. Paciulli, Simmons & Associates Ltd. Court/Case No. Richmond Circuit Court, Law No. LS-4378 Judge ...