Contracts – Public Contracts – Delay Damages (access required)

A statute that prevents government bodies from limiting damages in public contracts for delays caused by the government renders void limitations on damages in a public contract for construction work at Virginia Military Institute, the Virginia Supreme Court holds. The contract language on which VMI relies appears in the General Conditions (GC) that form a part ...