Where the prime contractor’s breach of contract claim would resolve whether a subcontractor failed to meet deadlines and whether the prime contractor suffered damages, its declaratory judgment claim was dismissed as redundant. Background In May 2011, the United States Army awarded BAE Systems Ordinance Systems Inc. a contract to design and construct a power plant. BAE executed ...