Virginia Lawyers Weekly//November 23, 2025//
Virginia Lawyers Weekly//November 23, 2025//
Where the operator of a gas pipeline sought to perform mitigation work to prevent the pipeline from being damaged by mining activities, and the owner of the land refused to allow access, the court entered an injunction allowing the operator to access the pipeline.
Background
Columbia Gas Transmission operates a natural gas pipeline that runs across a parcel of land owned by RDFS LLC. Columbia possesses an easement to operate and maintain the pipeline on RDFS’s parcel. After learning that a coal company was planning to mine beneath the parcel, Columbia concluded that it needed to unearth the pipeline and perform significant mitigation work to prevent the pipeline from being damaged by the subsidence.
Columbia approached RDFS to discuss the proposed mitigation work. RDFS contended then, as it does now, that the work exceeded the scope of Columbia’s easement. RDFS insisted that Columbia needed to acquire additional access rights to the parcel.
Columbia brought suit and the district court granted a preliminary injunction allowing Columbia to go forward with its mitigation efforts.
Law of the case
RDFS contends that the district court’s conclusion that Columbia had been unable to acquire from RDFS the right to conduct mitigation operations on the parcel—the third element of the district court’s ruling on Columbia’s claim under the Natural Gas Act—constitutes the “law of the case,” thereby requiring this court to vacate the district court’s grant of the preliminary injunction. This court disagrees.
To be sure, the district court’s preliminary finding that Columbia possessed an easement granting it access to the parcel could be read to contradict its later conclusion in granting Columbia’s motion for partial summary judgment that Columbia was unable to acquire the necessary right by contract. If Columbia already possessed the necessary property right, then it goes without saying that it was able to acquire that right. Even if this court were to read the district court’s order on the alternative claims as internally contradictory, however, the law of the case doctrine would not control this court’s review of the preliminary injunction ruling.
The law of the case doctrine is merely “a prudent judicial response to the public policy favoring an end to litigation,” and courts may revisit their prior decisions when circumstance so require. This court generally adheres to the law of the case doctrine when reviewing its own prior decisions.
The law of the case doctrine does not, and indeed cannot, limit the power of an appellate court to review a lower court decision. A court of appeals can affirm or reverse a district court judgment on any ground supported by the record, including grounds rejected by the district court or that undermine the reasoning of a different ruling by the district court.
The district court also did not defy the law of the case when it granted the preliminary injunction. This is because the law of the case doctrine applies only to rulings made at a “subsequent stage in the same case.” Here, the district court granted the preliminary injunction and the partial summary judgment in the same order. The law of the case doctrine does not apply to simultaneous rulings.
RDFS’s argument that the partial summary judgment ruling should be considered a final determination that supersedes the district court’s preliminary finding similarly fails. A ruling on a motion for partial summary judgment is not a final determination because it is subject to reconsideration under Federal Rule of Civil Procedure 54(b).
Easement
RDFS contends that the district court erred in concluding that Columbia’s easement likely grants access to RDFS’s parcel to conduct mitigation work. The court again disagrees.
Columbia’s easement conveys broad authority. It permits Columbia to “operate, maintain, replace, and finally remove” its pipeline “through all that certain tract of land” which makes up the parcel. RDFS nevertheless argues instead that, because the easement does not specify the boundaries of Columbia’s right of way, the easement is vague and its scope must be limited by extrinsic evidence of Columbia’s prior use of the parcel.
The court again disagrees. The scope of Columbia’s easement is sufficiently broad to include the mitigation work. Columbia’s prior use does not change or diminish the scope of the maintenance right. West Virginia common law makes clear that power companies retain the right, under a general right-of-way easement like the one at issue here, to access land to maintain and repair equipment to the extent necessary for the safe and effective operation of its equipment, in accordance with the original easement.
Affirmed.
Columbia Gas Transmission LLC v. RDFS LLC, Case No. 24-1387, July 29, 2025. 4th Cir. (Berner), from NDWVA at Wheeling (Bailey). Joy Melina Diaz Llaguno for Appellant. Nicolle Renee Snyder Bagnell for Appellee. VLW 025-2-291. 11 pp.